The district magistrate of a city has decided to reconstruct the most frequented street of the city. He plans to block the street for the duration of the work, which will cause considerable inconvenience to the people of the city. The project has three parallel paths defined as the following: Path A-B-C-H will take 16 days. Path A-D-E-H will take 22 days. Path A-F-G-H will take 30 days. In the
given scenario, which of the following statements is true?
A) The expected duration of the project is 68 days.
B) Activities B, D, and F have an earliest starting time of 0.
C) Path A-D-E-H has the largest slack time.
D) Path A-F-G-H is the critical path.
D
Business
You might also like to view...
If the activity level increases 10%, total variable costs will
a. remain the same. b. increase by more than 10%. c. decrease by less than 10%. d. increase 10%.
Business
The compensatory approach runs the risk of increased legal troubles due to different weightings provided by different experts
Indicate whether the statement is true or false
Business