An activity in a network diagram has an optimistic time estimate of five days, a most likely time estimate of seven days, and a pessimistic time estimate of 15 days. Its expected time is _________________.

a) 5 days
b) 7 days
c) 8 days
d) 10 days
e) 15 days

c) 8 days