The goal programming model for this problem has how many constraints?
Riverside Industries makes two products and each product is processed in three departments. The time requirements for each product in each department are given below. The profit for each product is also provided as well as the available hours in each department.
Product Department A Department B Department C Profit
1 3 4 2 1
2 2 1 2 2
Available Hours 600 400 400
Management wants to achieve three goals. The first two goals are equal in priority.
Priority 1: Produce at least 125 units of product 1.
Priority 1: Produce at least 80 units of product 2.
Priority 2: Achieve a profit of at least 300.
A) 3
B) 4
C) 6
D) 7
Answer: C
You might also like to view...
Treating each customer seperately and giving the perception that he or she is being treated as a unique segment by delivering personalized products and services is known as:
A) selective marketing. B) mass marketing. C) sales orientation. D) mass customization.
The proper command sequence to run ANOVA using your XL Data Analyst software is: COMPARE—3+ GROUP AVERAGES
Indicate whether the statement is true or false