The following table contains a list of activities, with precedence requirements and crash costs. All start and finish times and crash costs are on a per-week basis
a. Determine the project cost and duration without crashing.
b.
Determine the least expensive project cost if the duration is to be 10% shorter than normal project duration.
c. Determine the least expensive project cost if the duration is to be 20% shorter than normal project duration.
d. Create a graph that shows project expediting cost plotted as a function of the reduction in project duration.
Activity Normal Time Crash Time Normal Cost Crash Cost Predecessor
A 10 7 2000 2600
B 12 8 1500 2000 A
C 16 12 2200 3000 A
D 8 7 2500 3000 B
E 13 10 1950 2275 C
F 9 8 800 1000 D
G 24 29 3650 4000 E, F
H 17 14 1200 1800 G
a. Crash costs per week are shown in the table. The uncrashed project duration is 80 weeks at a cost of $15,800.
Activity Normal Time Crash Time Normal Cost Crash Cost Crash cost/week
A 10 7 2000 2600 $ 200
B 12 8 1500 2000 125
C 16 12 2200 3000 200
D 8 7 2500 3000 500
E 13 10 1950 2275 108.33
F 9 8 800 1000 200
G 20 15 3650 4000 70
H 17 14 1200 1800 200
b. The least expensive way to reduce the project duration by 10% (eight weeks) is by crashing activity G by five weeks at a cost of $70 per week, followed by activity B for three weeks at a cost of $125 per week. The total cost of the 72 week project is $725 extra, or $16,525.
c. Reducing the project by 20% from normal duration requires the actions indicated in part b, plus these actions. The reduction of activity B by another week for $125, activity A by three weeks at $200/week, activity H for three weeks at $200 per week, and activities E and F for one week each at $108.33 and $200 respectively. The total cost for the 64 week project is $2358.33 above the normal cost, or $18,158.33.
d.
You might also like to view...
Andrew and Martha license each other to use their patents. They agree not to license their patents to anyone else without asking for the other's permission first. Which of the following statements is true of Andrew and Martha's agreement?
A) This arrangement must be registered in court. B) This arrangement constitutes an unlawful tying arrangement. C) This arrangement constitutes unlawful cross-licensing. D) This arrangement is legal and valid.
Why is it important to identify the most appropriate cost drivers for a particular product?
A) so managers can identify the activities necessary to manufacture a product B) so managers can control product costs better C) so managers can predict product costs better and make better decisions D) B and C