During which of the following project planning activities do you use the information regarding tasks and resource availability to assign time estimates to each activity in the work breakdown structure?
A) Dividing the project into manageable tasks
B) Describing project scope, alternatives, and feasibility
C) Setting a baseline project plan
D) Developing a preliminary schedule
E) Developing a project scope statement
D
Explanation: D) The preliminary schedule will allow you to create target starting and ending dates for the project. Target dates can be revisited and modified until a schedule produced is acceptable to the customer.