Use the information in the table to sketch the network and compute early and late start times

Activity Time Predecessor
A 8
B 4 A
C 5 B, F
D 12 A
E 8 D
F 4 D
G 9 E, F
H 12 G
I 6 C, G
J 5 I
K 9 H
L 12 J, K

The early and late start times are shown in the table and the network is below:

Task Early Start Early Finish Late Start Late Finish
A 0 8 0 8
B 8 12 38 42
C 24 29 42 47
D 8 20 8 20
E 20 28 20 28
F 20 24 24 28
G 28 37 28 37
H 37 49 37 49
I 37 43 47 53
J 43 48 53 58
K 49 58 49 58
L 58 70 58 70

Business

You might also like to view...

What is the economy experiencing when a society cannot produce all the goods and services people wish to have?

a. scarcity b. externalities c. market failure d. communism

Business

Under IFRS, an item such as a convertible bond must be separated into two parts, showing one part in the Liability category and the other part in the Stockholders' Equity category

a. True b. False Indicate whether the statement is true or false

Business