Consider a project that has an expected completion time of 50 weeks and a standard deviation of 9 weeks. What is the probability that the project is finished in 57 weeks or fewer? (Round to two decimals.)
A) 0.68
B) 0.78
C) 0.22
D) 0.32
E) None of the above
B