Use the information in the table (all times are in days) to determine the lowest total cost for a 20-day project if the base cost for each activity finished in normal time is $1,000

Activity Normal Time Minimum Time Crash Cost ($/day) Predecessor
A 10 6 $70 --
B 6 3 $40 --
C 2 2 -- B
D 4 2 $60 C
E 6 4 $80 A
F 8 5 $90 D, E
A) $6,280
B) $6,390
C) $6,530
D) $6,740

A