XYZ project organization has one workstation that is capable of generating the drawings that their clients study before accepting XYZ's bid

XYZ is currently in the midst of three proposal projects and knows exactly when it will need to use the workstation. All other work to be done, both before and after the workstation is used, is scheduled such that it flows to the workstation and keeps it busy. Resources used after this step are less critical; so while the subsequent work and resources are important, they aren't viewed with the same reverence as the workstation. This is an example of:
A) Identifying a constraint.
B) Elevating a constraint.
C) Subordinating a system.
D) Exploiting a constraint.

C

Business

You might also like to view...

What is the purpose of the Alien Tort Claims Act?

A) It protects individuals from human rights abuses. B) It eliminates bribery in international business transactions. C) It inspects working conditions of factories in developing countries. D) It prohibits conflicts of interest among employees of international businesses.

Business

Senior management doesn't need to commit to the ERP project until it is near the go-live phase

Indicate whether the statement is true or false

Business