Describe three ways that line balancing and line flow layouts are similar to project management and three ways that they are different from project management

What will be an ideal response?

Answers may vary. Line balancing and project management both rely on the completion of predefined activities in the proper sequence. A line flow may have multiple feeder lines that supply subassemblies to the main line, similar to subcontractors working on the project in state of partial completion. Both have anticipated completion times that may not be reached if things don't go smoothly.

The time scale is radically different between line balancing and project management; projects tend to take much longer. Projects also tend to be one of a kind endeavors; line balancing is performed with the anticipation of high volumes of fairly standardized output. Line flows are created for more routine, process-oriented work that can be composed of standardized tasks. Projects are typically anything but routine and far from process-focused.

Business

You might also like to view...

In regards to benchmarking, which of the following statements is incorrect?

A) Benchmarking is the practice of comparing a company with other leading companies. B) The industry average is not a useful benchmark for evaluating a company. C) Providing common-size percentages in a graphical manner highlights differences. D) The two main types of benchmarks in financial statement analysis include benchmarking against the industry average and benchmarking against a key competitor.

Business

Angels fill a significant gap in the seed capital market

Indicate whether the statement is true or false

Business