Delaware Furniture Company constructs custom furniture. Job cost records during the second
and third quarters of 2009 are shown below.
Job No. Date Started Date Finished Total Cost of
Job
on July 1
Manufacturing Costs
Added in July
110 June 1 July 15 $32,840 $ 43,600
111 June 3 August 25 $18,100 $177,200
112 July 2 July 30 $145,000
113 July 6 July 31 $82,800
114 July 15 August 19 $126,400
What is the total cost of the July 31st finished goods inventory?
A) $82,800 B) $227,800 C) $209,200 D) $304,240
D