The network below represents a project being analyzed by the critical path method. Activity durations are indicated on the network
a. Identify the activities on the critical path.
b. What is the duration of the critical path?
c. Calculate the amount of slack time at activity H.
d. If activity I were delayed by ten time units, what would be the impact on the project duration?
(a) Critical activities are A-C-J-K; (b) The critical path is 26 time units; (c) Slack at H is 9 units; (d) I has 11 units slackāa ten unit delay would have no impact on the project.
Task Early Start Early Finish Late Start Late Finish Slack
A 0 5 0 5 0
B 0 3 6 9 6
C 5 16 5 16 0
D 0 4 9 13 9
E 3 10 9 16 6
F 4 10 15 21 11
G 3 7 17 21 14
H 4 7 13 16 9
I 10 15 21 26 11
J 16 22 16 22 0
K 22 26 22 26 0
Project 26
You might also like to view...
Nash & Associates is a firm that takes care of all export procedures on behalf of its clients. In exchange for a fee, the firm acts as the liaison between domestic manufacturers and prospective foreign buyers
It has access to established distribution networks in other countries that domestic small-scale producers are unlikely to have, and facilitates communication between foreign importers and domestic producers. Nash & Associates is most likely a(n) ________. A) domestic-based export merchant B) domestic-based export agent C) cooperative organization D) export-management company E) direct exporter
The Six Sigma DMAIC phase that identifies the problem statement of a project is
A) measure. B) define. C) analyze. D) investigate.