Jacquie Welkener, operations manager for ABC Technologies, must schedule work for the next five days. Each unit takes 30 minutes to process. Available capacity is 8 hours per day
The production order quantities are 12, 18, 20, 13, and 17 for Monday through Friday, respectively. What should be the production plan?
Sixteen units should be produced each day. Thus, 4 units should be moved from Tuesday to Monday, 2 units should be moved from Wednesday to Tuesday, 2 units should be moved from Wednesday to Thursday, and 1 unit should be moved from Friday to Thursday.
You might also like to view...
A salesperson is selling the Greenacre Estate. An offer has been accepted, and the clos-ing will take place in two weeks. While the owners are out of town, the buyer asks if the closing can be put off for one day. The sales- person agrees on behalf of the owners, for she is sure they will not object. The salesperson's conduct is
a. acceptable. b. mandated. c. discouraged. d. prohibited.
You realize I am sure that a firm's Web page present company history, product information and employment opportunities
What will be an ideal response?