List any five important points to remember when defining work packages

What will be an ideal response?

The author lists seven important points to remember about defining a project work package:
The work package typically forms the lowest level in the work breakdown structure.
A work package has a deliverable result.
A work package has one owner.
A work package may be considered by its owner as a project in itself.
A work package may include several milestones.
A work package should fit organizational procedures and culture.
The optimal size of a work package may be expressed in terms of labor hours, calendar time, cost, report period, and risks.

Business

You might also like to view...

An important step in dealing with sexual harassment is to have written procedures on how employees should deal with such behavior.

a. true b. false

Business

The time that customers wait to be served at the delicatessen for a grocery store follows the uniform distribution between 0 and 7 minutes. What is the probability that a randomly selected customer will wait between 1 and 5 minutes at the deli?

A) 0.1429 B) 0.2857 C) 0.4286 D) 0.5714

Business