A major outcome and deliverable from project initiation and planning that reflects the best estimate of the project's scope, benefits, costs, risks, and resource requirements defines the:

A) Baseline Project Plan.
B) Information Systems Plan.
C) Mission Statement.
D) Resource Requirements Statement.
E) Systems Service Request.

A
Explanation: A) The Baseline Project Plan (BPP) becomes the foundation for the remainder of the development project. It is an internal document used by the development team but not shared with customers.