What potential biases exist in project selection if Nico Manufacturing did not adjust for the difference in risk between Projects X and Y (See Table 11.10)
What will be an ideal response?
The danger of not accounting for differences in project risk is that the firm may potentially chose unacceptable high-risk projects (with negative NPVs) over potentially acceptable low-risk projects (with positive NPVs).