The project team toiled long into the night to develop consequence of failure scores and probability of failure scores as indicated below. What is the overall risk factor for the project?
Maturity 0.7 Cost 0.4
Complexity 0.6 Schedule 0.
6
Dependency 0.8 Reliability 0.8
Performance 0.9
A) Less than or equal to 0.7
B) Greater than 0.7 but less than or equal to 0.8
C) Greater than 0.8 but less than or equal to 0.9
D) Greater than 0.9
D
You might also like to view...
In large-scale projects, and especially in cases in which the data entry is performed by a subcontractor, researchers utilize a data code book which identifies (1 ) the questions on the questionnaire, (2 ) the variable name or label that is
associated with each question or question part, and (3 ) the code numbers associated with each possible response to each question. Indicate whether the statement is true or false
Which of the following acceptances is allowed for an offer under common law?
A) mirror image rule acceptance B) open term acceptance C) deposited rule acceptance D) additional terms acceptance