When all the tasks necessary to complete a project do not need to be done in any particular order, the project would be documented with a/n:

a. SWOT analysis.
b. Organic line of tasks.
c. Staircase mission statement.
d. Linear time line.

Answer: b
Feedback: When all the tasks necessary to complete a project do not need to be done in any particular order, this project would be documented with an organic line of tasks.