Given an activity's optimistic, most likely, and pessimistic time estimates of 2, 5, and 14 days respectively, compute the PERT expected activity time for this activity

A) 6
B) 7
C) 9
D) 5
E) None of the above

A

Business

You might also like to view...

The function of a __________ is limited to soliciting, identifying, and referring potential real estate clients to brokers, agents, or principals in exchange for a fee.

a. finder b. appraiser c. home inspector d. mortgage loan originator (MLO)

Business

While the lowering of trade barriers made globalization of markets and production a theoretical possibility, which of the following has made it a tangible reality?

A. The advances in communication, information processing, and transportation technologies B. The rise of communism and the need for independent economies on a global scale C. The increasing diversity in consumer tastes and preferences worldwide D. The increasing differences in the material culture the world over E. The decreasing significance of the World Trade Organization

Business