A project consists of four activities with information as shown in the table. What is the overall standard deviation of the project?
Activity Predecessor Length Variance
A -- 10 4
B A 12 3
C B 16 5
D C 14 6
A) 24
B) 18
C) 8.41
D) 4.24
D