What is the total project budget in this time-phased budget?
Activity January February March April
Survey 8,000
Design 5,250 4,500
Dirt 6,700
Foundation 12,550
Framing 37,250
Plumb 7,800
Wire 5,500
A) $85,450
B) $87,550
C) $82,050
D) $86,550
B