List all the 3-element subsequences contained in the data sequence for part (a) (assuming the timing constraints are flexible).
What will be an ideal response?
This will include all the subsequences in part (b) as well as the following:
< {1, 2, 3} {2} {4} > < {1, 2, 3} {3} {4} >
< {1, 2, 3} {2, 3} {4} > < {1, 2} {2} {4} >
< {1, 2} {3} {4} > < {1, 2} {2, 3} {4} >
< {2, 3} {2} {4} > < {2, 3} {3} {4} >
< {2, 3} {2, 3} {4} > < {1} {2} {2, 4} >
< {1} {2} {3, 4} > < {1} {2} {2, 3, 4} >
< {3} {2} {2, 4} > < {3} {2} {3, 4} >
< {3} {2} {2, 3, 4} > < {1, 3} {2} {2, 4} >
< {1, 3} {2} {3, 4} > < {1, 3} {2} {2, 3, 4} >
You might also like to view...
If 9/3/2021 is the contents of B3, what would be the result of =MONTH(B3 )?
A) 9/30/2021 B) 44442 C) 9 D) September E) None of the above
Rewrite the clear blue program to maximize blue (i.e., set it to 255) instead of clearing it. Is this useful? Would the red or green versions of the maximize function be useful? Under what conditions?
What will be an ideal response?