List three areas in which process models may differ from one another.
What will be an ideal response?
• Overall flow and level of interdependencies among tasks
• Degree to which work tasks are defined within each framework activity
• Degree to which work products are identified and required
• Manner in which quality assurance activities are applied
• Manner in which project tracking and control activities are applied
• Overall degree of detail and rigor of process description
• Degree to which stakeholders are involved in the project
• Level of autonomy given to project team
• Degree to which team organization and roles are prescribed