When contractual claims are defaulted due to the failure of a project to be completed and delivered:

A) The client firm should file an ex-gratia claim.
B) The client firm may have some legal claim to punitive damages.
C) The project firm should file an ex-gratia claim.
D) The project firm may have some legal claim to recovery.

B