The guiding philosophy behind factoring a project into detailed activities is
A) top-down design with successive refinement.
B) to schedule all activities according to CPM methodology.
C) to use analytic flowcharts to factor a project into modules.
D) to allow individual personnel to choose their own assignments.
Answer: A