An activity performed by a subcontractor is scheduled for 20 weeks at an anticipated cost of $100,000. Due to slippage on the critical path you need to reduce this activity by three weeks
If the subcontractor informs you that the activity can be completed in 16 weeks for $200,000, what is the slope for the activity?
A) $5,000 per week
B) $33,333 per week
C) $25,000 per week
D) $12,500 per week
C
You might also like to view...
Which of the following is the best example of an anchor store?
A) a freestanding store such as IKEA B) an upscale retailer such as Williams-Sonoma in a lifestyle center C) a department store such as Macy's in a shopping center D) a kiosk selling perfume or jewelry in a shopping center E) a small restaurant in a strip center
In the statement of cash flows, the cash flows from financing activities result from debt and equity financing transactions; including incurrence and repayment of debt, cash inflow from the sale of stock, and cash outflows to repurchase stock or pay
cash dividends. Indicate whether the statement is true or false