Cyclone Appliances has developed a new European-style convection oven that will be made on an assembly line. The schedule requires 80 ovens in an 8-hour day. The assembly includes seven tasks
The table below indicates the performance time and the sequence requirements for each task.
Task Performance Time (minutes) Task must follow Task listed below
A 1
B 2 A
C 3 B
D 2 B
E 4 C, D
F 1 E
G 2 F
(a) What is the cycle time for this assembly operation?
(b) What is the theoretical minimum number of workstations?
(c) Draw the precedence diagram.
(a) The cycle time is 480 minutes per day/80 ovens = 6 minutes/oven.
(b) The theoretical minimum number of workstations is the sum of all task times, 15 minutes, divided by the cycle time, 6 minutes; 15/6 = 2.5 or 3 workstations.
(c) The precedence diagram appears below.
You might also like to view...
In a short essay, list and discuss the three ways in which researchers may assess validity
What will be an ideal response?
The ________ requires certain contracts to be in writing
A) part performance exception B) common law of contracts C) equal dignity rule D) Statute of Frauds